Councillors agree to spend extra £11.7 million on Kex Gill scheme on A59 between Harrogate and Skipton

Senior North Yorkshire councillors say they have no choice but to spend an extra £11.7 million to “end the misery of Kex Gill once and for all”.

The investment agreed on Tuesday (May 13) by members of North Yorkshire Council’s executive committee takes the cost for the A59 Kex Gill realignment project to £82.5m.

The scheme was originally budgeted to cost £68.8m, with an extra £2m already approved by councillors.

Hide Ad
Hide Ad

Councillors were told however that the total cost of the scheme was likely to increase further, with councillors agreeing a further contingency fund to be used if necessary.

Senior councillors at North Yorkshire Council have agreed to spend an extra £11.7 million on the Kex Gill scheme on the A59 between Harrogate and SkiptonSenior councillors at North Yorkshire Council have agreed to spend an extra £11.7 million on the Kex Gill scheme on the A59 between Harrogate and Skipton
Senior councillors at North Yorkshire Council have agreed to spend an extra £11.7 million on the Kex Gill scheme on the A59 between Harrogate and Skipton

The work will create a four-kilometre bypass around a section of the east-west route near Blubberhouses, which has closed repeatedly over the years due to landslips.

Asking senior councillors to agree to the extra spending, Councillor Keane Duncan, executive member for highways and transportation, said: “Of course it’s extremely frustrating that we’re now seeing extra costs.

“The costs primarily relate to the delayed commencement of works, as well as essential design changes and poor ground conditions that we encountered on site

“These costs could not have been foreseen.

Hide Ad
Hide Ad

"They are not the council’s fault – but it is the unfortunate reality that it is us, the council and the taxpayers, that are obliged to pick up the bill for these extra costs.

“We simply don’t have a choice if we want to protect this key east-west route into the future and of course, free locals and visitors from the misery of repeat closures.”

The meeting heard that part of the extra costs had arisen because of the Department for Transport’s later than expected award of funding for the scheme.

The council’s contractor John Sisk & Son can seek additional payment for extra costs for dealing with unexpected changes, known as a ‘compensation event’.

Hide Ad
Hide Ad

Councillor Duncan said that the council were “not pushovers” and were scrutinising every request for compensation “robustly”.

“We have actually rejected a number of compensation requests outright.

"We are prepared to reject more in the future.”

But he added: “The choice before us today is not much of a choice at all.

“It’s either reject the release of the £11.7m that’s required in effect halting this scheme that we know is vitally important in safeguarding the A59.

Hide Ad
Hide Ad

“That means more landslips, more disruption, more costs, or agree to release the £11.7m and the scheme progresses without delay keeping us on track in delivering this essential upgrade, protecting the A59 future for thousands of people who rely on it and ending the misery of Kex Gill once and for all.

“It’s not a decision we want to make, but I feel very much it is a decision we have to make.”

Councillors were told the scheme was the most ambitious highways project ever undertaken by the authority due to the terrain, the height of the route and because it was a sensitive area for wildlife.

The road has been closed 15 times since 2000 and has cost the authority £6m to keep open during that time.

The council says the work is on track to be completed in spring next year.

Comment Guidelines

National World encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

News you can trust since 1836
Follow us
©National World Publishing Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice