Council provides update on £82.5 million Kex Gill scheme on A59 between Harrogate and Skipton

North Yorkshire Council has provided an update on the £82.5 million Kex Gill realignment scheme on A59 between Harrogate and Skipton.

Progress continues to be made on the major infrastructure project, with several key elements of the new route now taking shape.

A natural stone retaining wall is currently being constructed at the west end of the scheme, while work has also begun on installing a culvert at North Moor Road.

The culvert will take water beneath the new carriageway and discharge it into Hall Beck, forming part of a comprehensive drainage system designed to improve the long-term resilience of the route.

North Yorkshire Council has provided an update on the £82.5 million Kex Gill realignment scheme on A59 between Harrogate and Skiptonplaceholder image
North Yorkshire Council has provided an update on the £82.5 million Kex Gill realignment scheme on A59 between Harrogate and Skipton

Work has continued to backfill the large underpass visible from the old road, which will then be followed by cladding the exposed concrete walls in natural stone.

Drainage works along the new carriageway are ongoing, and waterproofing works are continuing on the bridge deck at Blubberhouses Bridge.

Landscaping has also commenced, with tree planting under way and grass seeding taking place using a wildflower mix.

However, motorists are being warned to expect temporary disruption over the coming weeks.

North Moor Road is closed for eight weeks at its junction with the A59 from Monday, March 2.

Two-way traffic is in place at the same junction for the same period.

Two-way traffic lights will remain at Blubberhouses Bridge on the A59 until mid-May.

In addition, Church Hill is scheduled to close at its junction with the A59 for eight weeks, currently expected to begin in early May.

Overnight road closures will also be required towards the end of the scheme to allow for final surfacing works.

Despite the restrictions, the council has confirmed the project remains on schedule, with the new stretch of road on track to open in June.