This is why crucial £82m building project near Harrogate may cause road closures throughout summer
Readers have got in touch with the Harrogate Advertiser with their fears that disruption around the building of a new section of the A59 at Kex Gill will last longer than has been advertised.
After North Yorkshire Council announced that work was nearing completion on the 2.5mile stretch of road bypassing the landslip-prone section of the A59 between Skipton and Harrogate, readers said not only were temporary traffic lights still causing disruption now but that they feared that would continue into late August.
The much-delayed and much-needed £82.5 million scheme to fix a key part of a well-used road in far from easy terrain had until March been on schedule to open in June.
North Yorkshire Council then said the completion date on this complex project prompted by regular landslips at Kex Gill would be mid-July.


But readers are now voicing doubts. Whether this is case of a glass half full or a glass half empty by local motorists, the most recent statement by the local authority suggests they have a point.
What North Yorkshire Council says about work taking place as part of the A59 Kex Gill project:
Current work
Drainage installation is ongoing, while surfacing contractors are due to return this month, says the council.


At Hall Lane, removal of the existing bridge is underway, alongside works to tie in the new road at both ends. Drainage and preparation for surfacing is also taking place at the western end.
Maintenance at Blubberhouses Bridge also continues, including waterproofing to minimise future disruption. Construction of the new bridleway linking Fewston Reservoir car park to North Moor Road is also progressing well.
Coming next month
As the scheme nears completion, the council says traffic management will be required to allow the final elements of construction to be carried out safely. North Moor Road will reopen under three-way traffic lights from now until mid-June.


Two-way traffic lights will remain in place at Blubberhouses Bridge for stabilisation and waterproofing works.
Work in July and August
From early July, the junction of Church Hill with the A59 will close for "about eight weeks” to enable construction of the new junction layout.
During this period, a signed diversion will operate via the B6451, Farnley Lane and Newall Carr Road, Otley.
Towards the end of the scheme, overnight closures of the A59 will be required to complete the final surfacing at both tie in points, with dates to be confirmed.
Benefits of Kex Gill project
The Kex Gill project is the most ambitious highways scheme ever undertaken by North Yorkshire Council. The new section of the A59 will replace the existing road, where there have been 15 landslips since 2000, causing significant disruption for the public and costing more than £6 million to repair.
North Yorkshire Council’s executive member for highways and transport, Coun Malcolm Taylor, said the project was approaching the finish line.
“The benefits of the new route will be felt for decades to come, providing a safer, more reliable connection for residents, businesses and visitors," he said.
As well as the construction of the new carriageway, the project encompasses new bridleways and footpaths, four kilometres of natural stone walls, two balancing ponds, and an extensive environmental scheme to enrich local habitats, including planting 12,000 trees and installing several bird and barn owl boxes.